Yaentu
Type
Mini hydropower plant
Capacity
10 MW
Location
Central Sulawesi
Scope of Work
Detailed engineering design, civil construction, hydro mechanical works, weir, intake, sandtrap, flushing, waterway, headpond, penstock and powerhouse
Status
Completed

Project
Overview
Project Yaentu is a run-of-river hydropower plant located in Poso, Central Sulawesi. Construction began in December 2020 and the plant has been operating commercially as scheduled since October 2024.
The plant has a capacity of 10 MW, with an estimated energy production of around 63,011 MWh per year. With a net head of up to 165 meters, this plant uses two horizontal Francis turbines for power generation.